Why are CPM, GERT, and PERT not considered sufficient to create a project schedule?5
Q: Why are CPM, GERT, and PERT not considered sufficient to create a project schedule?
- 1All three are tools and techniques of schedule development, not the actual schedulefalse
- 2As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitationstrue
- 3They are sufficient. Each calculates early and late start and finish dates for each activityfalse
- 4They are Monte Carlo techniques used to provide what-if analysis for adverse external factors on a projectfalse
- Show AnswerHide Answer
- Workspace
Answer : 2. "As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations"
Explanation :
Answer: B) As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations Explanation: Answer A is tempting because it is true by definition, but Answer B is correct because it properly answers the question, in that these techniques do not take into account resource pool constraints. Answer C is incorrect because it provides possible early and late start and finish dates, but not the actual schedules. Answer D is incorrect because none of the the three are simulation techniques.