प्र: Iam looking to estimate the cost on a project, but I don't want to spend a lot of time on a  detailed analysis. I really want a ballpark figure. What options do I have?

  • 1
    None - Cost estimating requires details to be accurate
  • 2
    Use the cost of similar projects
  • 3
    Use a rule-of-thumb or per-square-foot estimate
  • 4
    Add up the costs on the WBS
  • उत्तर देखें
  • Workspace

उत्तर : 2. "Use the cost of similar projects"
व्याख्या :

Answer: B) Use the cost of similar projects Explanation: Although it is less accurate than adding up individual costs from the WBS, it is less time consuming. The trade-off is accuracy. Answer A is incorrect because to do a more accurate cost estimate, you need to delve into details. Answer C is tempting also, and possible, except we don't really know if the project in question can use perametric modeling . Answer D is incorrect because it takes the most time, but it is most accurate.

क्या आपको यकीन है

  त्रुटि की रिपोर्ट करें

कृपया संदेश दर्ज करें
त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई