जॉइन Examsbook
897 0

प्र: Subject matters experts (SMEs) are resources that are imperative to the succes of a project. Many times, project managers are not experts in the areas they are managing and frequently must rely upon other's expertise. In which scope - management process are SMEs first used?

  • 1
    Scope planning
  • 2
    Scope definition
  • 3
    Initiation
  • 4
    Scope verification
  • उत्तर देखें
  • Workspace

उत्तर : 3. "Initiation"
व्याख्या :

Answer: C) Initiation Explanation: Initiation is the first step in the scope management process, and expert judgment is one of the techniques routinely utilized. Answers A, B, and D are incorrect because they would come after the initiation process.

क्या आपको यकीन है

  त्रुटि की रिपोर्ट करें

कृपया संदेश दर्ज करें
त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई