Join ExamsbookAnswer : 3. "A manager external to the project"
A project charter is one of the key deliverables to come from the initiation process. The project charter should by issued by5
Q: A project charter is one of the key deliverables to come from the initiation process. The project charter should by issued by
- 1one or more functional managersfalse
- 2The head of the performing organizationfalse
- 3A manager external to the projecttrue
- 4The CFOfalse
- Show AnswerHide Answer
- Workspace
Answer : 3. "A manager external to the project"
Explanation :
Answer: C) A manager external to the project Explanation: The other answers could be accurate in specific situations, but their role alone does not meet the keyb criterion of being "external" to the project team. Answers A, B, and D are incorrect because these individuals are not external to the project.