Join Examsbook
791 0

Q: Management by projects views aspects of ongoing operations as projects in order to apply Project Management techniques to them. This can be used to describe an oranizational approach to the management of ongoing operations. Why would a company want to utilize this methodology on nonprojects?

  • 1
    To keep project managers employed
  • 2
    To provide better estimates about durations
  • 3
    To allow the utilization of PM tools, such as earned value, to calculate ROI
  • 4
    To specify the different phases within the operations
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "To allow the utilization of PM tools, such as earned value, to calculate ROI"
Explanation :

Answer: C) To allow the utilization of PM tools, such as earned value, to calculate ROI Explanation: Answer A is incorrect because project managers are not effectively utilized if they are always scheduling and coordinating resources for daily operations. Answer B is incorrect because project managers are not the best resource for providing estimates on daily operations and time allocations;people doing the actual work are the best resources. Answer D is incorrect because you do not specify different phases of ongoing operations.

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully