Q: Project Time Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Activity Sequencing ?

  • Show Answer
  • Workspace

Answer :
Explanation :

I.Inputs Project scope statement Activity list Activity attributes Milestone list Approved change requests II. Tools and Techniques Precedence Diagramming Method (PDM) Arrow Diagramming Method (ADM) Schedule network templates  Dependency determination Applying leads and lags  III. Outputs Project schedule network diagrams Activity list (updates) Activity attributes (updates) Requested changes