Get Started
637

Q: Project Time Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Schedule Control ?

  • Show Answer
  • Workspace

Answer :
Explanation :

I. Inputs Schedule management plan Schedule baseline Performance reports Approved change requests II. Tools and Techniques Progress reporting Schedule change control system Performance measurement Project management software Variance analysis Schedule comparision bar charts III. Outputs Schedule model data (updates) Schedule baseline (updates) Performance measurements Requested changes Recommended corrective actions Organizational process assets (updates) Activity list (updates) Activity attributes (updates) Project management plan (updates)

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today