Join ExamsbookAnswer : 3. "1/6"
X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?5
Q: X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?
- 11/3false
- 22/3false
- 31/6true
- 45/6false
- Show AnswerHide Answer
- Workspace
Answer : 3. "1/6"
Explanation :
Answer: C) 1/6 Explanation: Given X can do in 10 days => 1 day work of X = 1/10 Y can do in 15 days => 1 day work of Y = 1/15 1day work of (X + Y) = 1/10 + 1/15 = 1/6 Given they are hired for 5 days => 5 days work of (X + Y) = 5 x 1/6 = 5/6 Therefore, Unfinished work = 1 - 5/6 = 1/6