Q: Typically not referred to as a buffer type in critical chain project management is ______.
- 1Free Buffertrue
- 2Resource Bufferfalse
- 3Project Bufferfalse
- 4Feeding Bufferfalse
- Show AnswerHide Answer
- Workspace
Answer : 1. "Free Buffer"
Explanation :
Answer: A) Free Buffer Explanation: