जॉइन Examsbook
1348 0

प्र: Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work ?

  • 1
    3 days
  • 2
    2 days
  • 3
    6 days
  • 4
    12 days
  • उत्तर देखें
  • Workspace

उत्तर : 3. "6 days"
व्याख्या :

Answer: C) 6 days Explanation: From the given data, 12 children 16 days work,One child’s one day work = 1/192. 8 adults 12 days work,One adult’s one day’s work = 1/96. Work done in 3 days = ((1/96) x 16 x 3) = 1/2 Remaining work = 1 – 1/2 = 1/2 (6 adults+ 4 children)’s 1 day’s work = 6/96 + 4/192 = 1/12 1/12 work is done by them in 1 day. 1/2 work is done by them in 12 x (1/2) = 6 days.

क्या आपको यकीन है

  त्रुटि की रिपोर्ट करें

कृपया संदेश दर्ज करें
त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई