Join ExamsbookAnswer : 2. "100"
Pavan and Sravan are two persons. If Pavan works with his actual efficiency and Sravan twice of his actual efficiency then it takes 25 days to complete the work. But If Pavan works twice of his actual efficiency and Sravan with his normal efficiency then the work is completed in 20 days. How many days would it take if Sravan alone works with his actual efficiency (in Days)?5
Q: Pavan and Sravan are two persons. If Pavan works with his actual efficiency and Sravan twice of his actual efficiency then it takes 25 days to complete the work. But If Pavan works twice of his actual efficiency and Sravan with his normal efficiency then the work is completed in 20 days. How many days would it take if Sravan alone works with his actual efficiency (in Days)?
- 150false
- 2100true
- 370false
- 435false
- Show AnswerHide Answer
- Workspace
Answer : 2. "100"
Explanation :
Answer: B) 100 Explanation: Let the Efficiency of pavan be E(P) Let the Efficiency of sravan be E(S) Here Work W = LCM(25,20) = 100 Now, E(P+2S) = 100/25 = 4 ....(1) E(2P+S) = 100/20 = 5 ....(2) Hence, from (1) & (2) we get E(S) = 1 => Number of days Savan alone work to complete the work = 100/1 = 100 days.