If 15 men 4 hours per day works for 14 days get Rs.35/- then how many men required if the work is 8 hours per day for 10 days they get 50/- ?5
प्र: If 15 men 4 hours per day works for 14 days get Rs.35/- then how many men required if the work is 8 hours per day for 10 days they get 50/- ?
- 112false
- 213false
- 314false
- 415true
- उत्तर देखें
- Workspace
उत्तर : 4. "15"
व्याख्या :
Answer: D) 15 Explanation: We know M1×D1×H1W1 = M2×D2×H2W2 => 15×4×1435 = M×8×1050 => M = 15