After working for 8 days, Arun finds that only 13 rd of the work has been done. He employs Akhil who is 60% as efficient as Arun. How many days more would Akhil take to complete the work?5
Q: After working for 8 days, Arun finds that only 13 rd of the work has been done. He employs Akhil who is 60% as efficient as Arun. How many days more would Akhil take to complete the work?
- 124.5 daysfalse
- 226.6 daystrue
- 325 daysfalse
- 420 daysfalse
- Show AnswerHide Answer
- Workspace
Answer : 2. "26.6 days"
Explanation :
Answer: B) 26.6 days Explanation: Arun has completed 13rd of the work in 8 days Then he can complete the total work in 13 ---- 8 1 ---- ? = 24 days But given Akhil is only 60% as efficient as Arun Akhil =124×60100=140 Akhil can complete the total work in 40 days Now, remaining 2/3rd of work can be completed in 1 ------ 40 23 ------ ? = 26.66 days.