प्र: After working for 8 days, Arun finds that only 13 rd of the work has been done. He employs Akhil who is 60% as efficient as Arun. How many days more would Akhil take to complete the work?

  • 1
    24.5 days
  • 2
    26.6 days
  • 3
    25 days
  • 4
    20 days
  • उत्तर देखें
  • Workspace

उत्तर : 2. "26.6 days"
व्याख्या :

Answer: B) 26.6 days Explanation: Arun has completed 13rd of the work in 8 days Then he can complete the total work in 13 ---- 8  1 ---- ? = 24 days But given Akhil is only 60% as efficient as Arun Akhil =124×60100=140 Akhil can complete the total work in 40 days Now, remaining 2/3rd of work can be completed in  1  ------   40 23 ------   ?   = 26.66 days.