प्र: A work which could be finished in 11 days was finished 4 days earlier after 4 more men joined. The number of men employed was ?

  • 1
    7
  • 2
    8
  • 3
    9
  • 4
    10
  • उत्तर देखें
  • Workspace

उत्तर : 1. "7"
व्याख्या :

Answer: A) 7 Explanation: As the work is sameM1D1 = M2D2 Here Let the number of men employed was M=> 11M = 7(M+4)=> 11M - 7M = 28=> M = 7