प्र: A shopkeeper has a job to print certain number of documents and there are three machines P, Q and R for this job. P can complete the job in 3 days, Q can complete the job in 4 days and R can complete the job in 6 days. How many days the shopkeeper will it take to complete the job if all the machines are used simultaneously ?

  • 1
    4/3 days
  • 2
    2 days
  • 3
    3/2 days
  • 4
    4 days
  • उत्तर देखें
  • Workspace

उत्तर : 1. "4/3 days"
व्याख्या :

Answer: A) 4/3 days Explanation: Let the total number of documents to be printed be 12.  The number of documents printed by P in 1 day = 4.  The number of documents printed by Q in 1 day = 3.  The number of documents printed by R in 1 day = 2.  Thus, the total number of documents that can be printed by all the machines working simultaneously in a single day = 9.   Therefore, the number of days taken to complete the whole work = 12/9 = 4/3 days.