A man completes 5/8 of a job in 10 days. At this rate, how many more days will it take him to finish the job ?5
Q: A man completes 5/8 of a job in 10 days. At this rate, how many more days will it take him to finish the job ?
- 14false
- 26true
- 38false
- 47/2false
- Show AnswerHide Answer