A group of men can complete a job in K hours. After every 4 hours, half the number of men working at that point of time leave the job. Continuing this way if the job is finished in 16 hours, what is the value of K ?5
Q: A group of men can complete a job in K hours. After every 4 hours, half the number of men working at that point of time leave the job. Continuing this way if the job is finished in 16 hours, what is the value of K ?
- 17 hrsfalse
- 27.5 hrstrue
- 38 hrsfalse
- 48.25 hrsfalse
- Show AnswerHide Answer
- Workspace
Answer : 2. "7.5 hrs"
Explanation :
Answer: B) 7.5 hrs Explanation: Let there are L men job requires LK man hours. job completed in first 4 hrs = L x 4 = 4L job completed in next 4 hrs = 4 x L/2 = 2L job completed in next 4 hrs = 4 x L/4 = L job completed in last 4 hrs = 4 x L/8 = L/2 4L + 2L + L + L/2 = KL K = 7+1/2 = 7.5 hours.