A can do a work in 9 days, B can do a work in 7 days, C can do a work in 5 days. A works on the first day, B works on the second day and C on the third day respectively that is they work on alternate days. When will they finish the work ?5
Q: A can do a work in 9 days, B can do a work in 7 days, C can do a work in 5 days. A works on the first day, B works on the second day and C on the third day respectively that is they work on alternate days. When will they finish the work ?
- 1[7 + (215/345)] daysfalse
- 2[6 + (11/215)] daysfalse
- 3[6 + (261/315)] daystrue
- 4[5 + (112/351)] daysfalse
- Show AnswerHide Answer
- Workspace
Answer : 3. "[6 + (261/315)] days"
Explanation :
Answer: C) [6 + (261/315)] days Explanation: After day 1, A finishes 1/9 of the work. After day 2, B finishes 1/7 more of the total work. (1/9) + (1/7) is finished. After day 3, C finishes 1/5 more of total work. Total finished is 143/315. So, after day 6, total work finished is 286/315. Now remaining work = 29 /315 On day 7, A will work again Work will be completed on day 7 when A is working. He must finish 29/315 of total remaining work. Since he takes 9 days to finish the total task, he will need 261/315 of the day. Total days required is 6 + (261/315) days.