Q: You have started your own company based upon PMI methodologies and have been contracted by the government to develope a new interface for one of its computer applications. You develope a solution and win the bid for the contract but encounter problems at the end of the project when the customer says that you did not fullfill their needs. You are throughly shocked. What is your conclusion of the situation?

  • 1
    There are always more customers available
  • 2
    If the customer is not satisfied, the project is not successful
  • 3
    Change control management was not effective
  • 4
    The customer did not communicate very well
  • Show Answer
  • Workspace

Answer : 2. "If the customer is not satisfied, the project is not successful"
Explanation :

Answer: B) If the customer is not satisfied, the project is not successful Explanation: Answer A is incorrect because without satisfied customers, we do not have potential for new projects. Answer C is incorrect because the change control management process would have likely resolved this problem. Answer D is incorrect because it is the project manager's responsibility to seek communication with the customer to set realistic expectations.

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today