You are working on a new project to develop a new wireless product with ease - of - use features recommended by customers. It is as yet undetermined which features and the extent to which each feature will be incorporated into the product.You have a focus group that will continue to evaluate the features as the project goes forward.The focus group is authorized to suggest changes, as are your engineers and the quality department.As a project manager, what will help you most to minimize the effect of these changes?5
1056 5b5cc7cce4d2b4197775104e
Q: You are working on a new project to develop a new wireless product with ease - of - use features recommended by customers. It is as yet undetermined which features and the extent to which each feature will be incorporated into the product.You have a focus group that will continue to evaluate the features as the project goes forward.The focus group is authorized to suggest changes, as are your engineers and the quality department.As a project manager, what will help you most to minimize the effect of these changes?
- 1A change management planfalse
- 2A scope management plantrue
- 3Do not continue with the project until all of the features are clearly defined in the scope statement and scope definition.false
- 4This is an expected part of every project. A good project manager will have a communications plan in place to be sure everyone knows what is happening on the project.false
- Show Answer
- Workspace
- Discuss