Why are CPM, GERT, and PERT not considered sufficient to create a project schedule?5
1233 5b5cc7cce4d2b41977751035
Q: Why are CPM, GERT, and PERT not considered sufficient to create a project schedule?
- 1All three are tools and techniques of schedule development, not the actual schedulefalse
- 2As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitationstrue
- 3They are sufficient. Each calculates early and late start and finish dates for each activityfalse
- 4They are Monte Carlo techniques used to provide what-if analysis for adverse external factors on a projectfalse