P, Q, and R can do a job in 12 days together. If their efficiency of working be in the ratio 3 : 8 : 5, Find in what time Q can complete the same work alone?5
1588 5b5cc698e4d2b4197774c61d
Q: P, Q, and R can do a job in 12 days together. If their efficiency of working be in the ratio 3 : 8 : 5, Find in what time Q can complete the same work alone?
- 136 daystrue
- 230 daysfalse
- 324 daysfalse
- 422 daysfalse
- Show Answer