Q: P can do a piece of work in 5 less days than Q. If both of them can do the same work in 1119days, in how many days will Q alone do the same work  ?

  • 1
    24 days
  • 2
    25 days
  • 3
    20 days
  • 4
    19 days
  • Show Answer
  • Workspace

Answer : 2. "25 days"
Explanation :

Answer: B) 25 days Explanation: Let Q complete that work in 'L' days   => 1L + 1L-5 = 9100   => 9L2-245L+500=0   L = 25 days.