A work which could be finished in 11 days was finished 4 days earlier after 4 more men joined. The number of men employed was ?5
1409 5b5cc6e1e4d2b4197774ebb6
Q: A work which could be finished in 11 days was finished 4 days earlier after 4 more men joined. The number of men employed was ?
- 17true
- 28false
- 39false
- 410false
- Show Answer
- Workspace
- Discuss