Get Started
1056

Q: A can do a piece of work in 15 days and B can do it in 16 days and C can do it 24 days. They started the work together and A leaves after 3 days and B leaves after 4 days from the beginning. How long will work lost ?

  • 1
    10 2/3 days
  • 2
    13 1/5 days
  • 3
    12 2/3 days
  • 4
    11 5/7 days
  • Show Answer
  • Workspace

Answer : 2. "13 1/5 days"
Explanation :

Answer: B) 13 1/5 days Explanation: 3/15 + 4/16 + x/24 = 1 ⇒x=1315

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today